Day 7 – Tuesday 21 November

The cloudy days continue with the threat of rain a constant.

The boys worked on preparing the side garden for the installation of the retaining wall.  To achieve this the plants were removed from both sides of the existing path and then the large concrete pavers were moved across closer to the house so that we now won’t have a garden too close to the building.

Pavers being moved across.

More Posts

Day 13

Day 13 – Wednesday 29th November At 3pm on Tuesday the rain came in and

Day 12

Day 12 – Tuesday 28 November Today the boys continued to remove soil from the

Day 11

Day 11 – Monday 27th November Damo and John continued with the retaining wall slotting

Day 10

Day 10 – Friday 24th November The day of the retaining wall. …and now to

Day 9

Day 9 – Thursday 23 November The detailed measuring and placement of the steel posts

Day 8

Day 8 – Wednesday 22nd November The auger was attached to the digger and the

Day 6

Day 6 – Monday 20th November Disappointingly work on site was delayed by a week.

Day 4

Thursday 9th November Today the mighty little digger arrived. Access was difficult. First of all

Day 3

Wednesday 8th November The demolition continues.